Add minutes from last meeting

Signed-off-by: Lance Albertson <lance@osuosl.org>
master
Lance Albertson 1 day ago
parent c635af6e18
commit 4f90a67c6a

@ -0,0 +1,46 @@
---
title: Meeting Minutes 2026-01-06
date: 2026-01-06
attendees:
- lancealbertson,oregonstateuniversity
- jameskulina,openpowerfoundation

draft: false
---

## Call to order

### Anti-trust reminder

This is a reminder that all OpenPOWER Foundation activities are subject to strict compliance with the OpenPOWER Foundations Antitrust Guidelines. Each individual participant and attendee at this meeting is responsible for knowing the contents of the Antitrust Guidelines, and for complying with the Antitrust Guidelines. Copies of the Antitrust Guidelines are available at : [HERE](https://files.openpower.foundation/s/k5Hny649q3XHSqk)

## Agenda

1. OPF HUB Requests
* New
* Active
* Ongoing
- [#201126: Request by Selkies-GStreamer for OpenPOWER HUB access through Oregon State University Open Source Lab](https://requests.openpower.foundation/Ticket/Display.html?id=201126)
- No new updates
- [#200816: Request by AMD ROCm 9 for OpenPOWER HUB access through Oregon State University Open Source Lab](https://requests.openpower.foundation/Ticket/Display.html?id=200816)
- No new updates
- [#202910: Request by Ublu for OpenPOWER HUB access through Oregon State University Open Source Lab](https://requests.openpower.foundation/Ticket/Display.html?id=202910)
- No new updates
- [#203729: Request by Debusine for OpenPOWER HUB access through Oregon State University Open Source Lab](https://requests.openpower.foundation/Ticket/Display.html?id=203729)
- No new updates
- [#203488: Request by Deep learning workloads for OpenPOWER HUB access through Oregon State University Open Source Lab](https://requests.openpower.foundation/Ticket/Display.html?id=203488)
- No new updates

2. Other Items
* Data center move
- General status update
- Network to Corvallis setup and working
- 4 racks have been plumbed for networking
- Moved some initial OSL internal gear in Dec
- OPH move timeline
- No specific dates yet, still likely sometime in late Jan 2026
- Will move systems that are currently shutoff first and then migrate VMs

## Next meeting

{{< localdatetime date="2026-01-20" time="22:00" >}}

@ -0,0 +1,49 @@
---
title: Meeting Minutes 2026-02-03
date: 2026-02-03
attendees:
- lancealbertson,oregonstateuniversity
- jameskulina,openpowerfoundation

draft: false
---

## Call to order

### Anti-trust reminder

This is a reminder that all OpenPOWER Foundation activities are subject to strict compliance with the OpenPOWER Foundations Antitrust Guidelines. Each individual participant and attendee at this meeting is responsible for knowing the contents of the Antitrust Guidelines, and for complying with the Antitrust Guidelines. Copies of the Antitrust Guidelines are available at : [HERE](https://files.openpower.foundation/s/k5Hny649q3XHSqk)

## Agenda

1. OPF HUB Requests
* New
- [#204573: MetaGuard AI - OPF HUB FPGA card access](https://requests.openpower.foundation/Ticket/Display.html?id=204573)
- Reserved oph12
- Installed OS, waiting on ssh key
* Active
* Ongoing
- [#201126: Request by Selkies-GStreamer for OpenPOWER HUB access through Oregon State University Open Source Lab](https://requests.openpower.foundation/Ticket/Display.html?id=201126)
- No new updates
- [#200816: Request by AMD ROCm 9 for OpenPOWER HUB access through Oregon State University Open Source Lab](https://requests.openpower.foundation/Ticket/Display.html?id=200816)
- No new updates
- [#202910: Request by Ublu for OpenPOWER HUB access through Oregon State University Open Source Lab](https://requests.openpower.foundation/Ticket/Display.html?id=202910)
- No new updates
- [#203729: Request by Debusine for OpenPOWER HUB access through Oregon State University Open Source Lab](https://requests.openpower.foundation/Ticket/Display.html?id=203729)
- No new updates
- [#203488: Request by Deep learning workloads for OpenPOWER HUB access through Oregon State University Open Source Lab](https://requests.openpower.foundation/Ticket/Display.html?id=203488)
- No new updates

2. Other Items
* Data center move
- OPH move timeline
- All OPH OpenStack nodes have been moved
- Remaining systems (6) are alled reserved project systems
- Will be moving within the next week
- Contacting projects directly notifying them a few days before the move
- Roughly 90 systems have been moved, and around 170 are left to be moved
- Move should be completed by the end of March
## Next meeting

{{< localdatetime date="2026-03-03" time="19:30" >}}